The Big Build – Week 5

0 0
Read Time:33 Second

Thursday 5th July 2018

Work stopped as we were waiting for the big steel/lintel to go over the bi-fold doors.  Due in Friday so we’ll wait to see if it materialises!  Another quiet day tomorrow!


Wednesday 4th July 2018

Brickwork continued today as they bricked up over the lintels and continued building up the gable ends.

[easy-image-collage id=3896]

 


Tuesday 3rd July 2018

No workmen on site yesterday so a quiet day.  The lintels had arrived for the windows and patio door so they were working on getting all the brickwork in place so these can be put in situ.

[easy-image-collage id=3890]

About Post Author

Karen

Happy
Happy
0 %
Sad
Sad
0 %
Excited
Excited
0 %
Sleepy
Sleepy
0 %
Angry
Angry
0 %
Surprise
Surprise
0 %
Previous post The Big Build – Week 4
Next post The Big Build – Week 6

Average Rating

5 Star
0%
4 Star
0%
3 Star
0%
2 Star
0%
1 Star
0%

Leave a Reply

Your email address will not be published. Required fields are marked *